Agile foundation
- by Laurent
- in
- on 3 octobre 2022
Résumé de Quiz
0 of 10 Questions completed
Questions:
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
Vous devez d’abord complété le suivant :
Résultats
Résultats
0 of 10 Questions answered correctly
Your time:
Temps écoulé
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Catégories
- Pas classé 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Current
- Révision
- Répondu
- Exact
- Inexact
-
Question 1 of 10
1. Question
1. A software vendor has recently hired you to manage some of its key projects. During your orientation at the organization you were told that the organization has recently adopted Agile practices for project management. A chart was then shown to you where Agile and Kanban were shown as subset of Lean. What is your view on this?
ExactInexact -
Question 2 of 10
2. Question
2. You have recently been hired by a major airport operator to head its project management office. The PMO has been following a waterfall-based project management approach consistently across all projects. You want to pilot Agile approaches on a couple of new projects and see how these approaches can benefit the organization. However, the team members are not experienced in the use of Agile approaches. What should you do first?
ExactInexact -
Question 3 of 10
3. Question
3. You have been assigned a new project. The project involves disruptive technologies. The project scope is not clear which has introduced a lot of risk into the project. You have requested to use Agile to manage this project. Why?
ExactInexact -
Question 4 of 10
4. Question
4. You are an Agile process analyst and are assigned to work for Anu who is leading a complex Student Services Design project for a university. Anu insists that the team create highly detailed project plans before commencing the work. What should you do?
ExactInexact -
Question 5 of 10
5. Question
5. When introducing Agile methods to an organization that has historically managed all its project using predictive life cycles, which of the following approaches is more likely to succeed?
ExactInexact -
Question 6 of 10
6. Question
6. A project team is currently building a warehouse management system. Due to the complexity of the project and ambiguous requirements, the team decided to adopt an Agile management approach. If a higher rate of management process improvement is required by the project team, which of the following can help achieve this objective?
ExactInexact -
Question 7 of 10
7. Question
7. You are responsible for designing a new handheld gadget followed by a mass rollout to the market. The project has been requested as a result of your organization’s blue ocean strategy, and if successful, will create a market for its own. However there is a high degree of uncertainty around the requirements which can only be uncovered through prototyping. Which of the following approaches is most likely to succeed?
ExactInexact -
Question 8 of 10
8. Question
8. Your organization has been awarded a contract to develop and implement a new resource management system for a client based in Asia. Your development team is distributed across Europe. You are also planned to relocate the implementation team to the client location. What would be your biggest challenge in such a setup?
ExactInexact -
Question 9 of 10
9. Question
9. You are responsible for deploying a new supply chain management system for a client organization. You need to analyze the client organization’s current processes and procedures, design future-state processes in consultation with the subject matter experts at the client organization, and customize the supply chain system to suit these processes. According to the contract, all prototypes presented to the client must accompany user instruction sets. Your team is objecting to this documentation requirements and insist in developing a user manual only at the very end of the project. What should you do?
ExactInexact -
Question 10 of 10
10. Question
10. You have been hired by an organization to introduce Agile to its project management office. During one of your initial presentations to the team you have been asked a tough question: Is Agile an approach, a method, a practice, a technique, or a framework? What should be your response?
ExactInexact