Bonjour Delphine,
Good question :), regarding your first question it’s normal because a product increment should be usable and potentially releasable at the end of every Sprint, but it does not have to be released. Si if the question was with “may be released” instead of “must be released” the response will be yes.
Here the MUST is too restrictive and not align with the framework, regarding your second point the response is true because if at the end of a sprint an increment can be released, we need to have an increment at the end of the sprint to be able to have something releasable.
I hope my explanation was clear đ